Pick the rung for three tasks

Place three agency tasks on the ladder, price one step up against the task's own sum, and decide whether one agent should do all three.

casemediumExercise · 4 min · 17 of 75
On this page

Three tasks, three different rungs, and a founder who would rather build one agent for all of them. A rung too low costs incidents; a rung too high costs something every month.

The situation

The agency has approved three builds for this quarter. Assume staff at $30 an hour, the founder at $100, a month of 4.33 weeks, and the build estimates from the ladder lessons: about 15 minutes on rung 1, 12 hours on rung 2, 20 hours with tests on rung 3.

  • New client setup. 3 signed contracts a month. Each creates a project in the project tool, a shared folder and a client channel: 20 minutes by hand, no judgment.
  • Categorise bank transactions. 150 a week from the bank feed, 1 minute each, $20 per mis-post. One model call per transaction; anything it is unsure of goes to the operations manager's review queue by Friday. The accounting API fails a few times a week, and bank data may pass through no vendor except the model provider.
  • Screen CVs. 150 applicants per role, about one role a month, an answer promised within three days. The founder approves borderline applicants in two sittings a day, and a bias check on 40 saved CVs must pass before any prompt change goes live.

The founder's proposal: "One agent with the tools for all three."

The question

Place each task on a rung, price the step up to the next rung for one of them, and decide on the founder's proposal.