The feature request that adds six weeks

Choose which kind of no to give a sponsor who wants decline letters drafted by week 8, cost it in reviewer-hours, and name what would make it a yes.

casehardExercise · 4 min · 18 of 64
On this page

The sponsor's request is reasonable, visible, and six weeks long. The answer has to keep him, keep the date, and be given in the room.

The situation

Week 3 of 8. In the Friday meeting the VP of Claims asks whether the pilot can also draft the letter sent to the claimant when cover is declined after triage: about 15% of 1,200 claims a day, roughly 180 letters. The letters go out under the insurer's name and are regulated; a wrong one is a complaint to the ombudsman. Today a handler writes each from one of nine templates in about six minutes. Costed in your head: one week to agree the templates and the prohibited phrasings with the legal team; two weeks to build a rubric-graded eval of 100 letters, each graded by two reviewers in about four minutes, since free text has no exact match; one to two weeks of prompt iteration; one week assisted, with a handler editing every letter. Six weeks of calendar, and the two senior handlers who would grade them are labelling the triage gold set, which stands at 140 of 200. The VP adds that the board sees a demo in week 8 and "the letter is the bit they'll understand". Agreement on the triage eval is 90% against the 95% line. Sales is not in the room.

The question

Which of the three kinds of no do you give, what do you say to the VP in the room, and what would have to be true for the answer to be yes?

A strong answer · Rubric · Where answers go wrong

Write your answer first, then open